Johnson Senior High School: COMPLETED fall 2017
Johnson Senior High - completed remodeled spaces



-
Johnson Senior High School received significant building updates as the result of direct feedback from Johnson’s Facilities Master Plan community workshops and previously-planned building maintenance.
Johnson’s renovations included a building addition to provide a secure front entry and additional classrooms and support space for students and staff. Restrooms were also changed to an inclusive-restroom model to make them more accessible and safer for everyone. Planned maintenance work replaced worn-out electrical systems that increases the efficiency of the building and improves the learning environment.
The remodeling was done in two phases:
Phase 1: Summer 2016
- New boilers
- New roof
- New fire alarm system
- Plumbing replacement/new single-occupancy restrooms
Phase 2: Summer 2017
- Building addition with new front entry
- Replacement of flooring, ceiling, paint and lighting in the cafeteria and corridor
Work was completed in time for the beginning of the school year in fall 2017.