Systems and Infrastructure Programs
Project type: HVAC replacement
Phase: Construction or Planning
Project budget for all 6 projects: $28,340,000; funded by American Rescue Plan, COVID-19 relief federal funding
Timeline: 2023-2024
Active construction sites:
Construction begins in 2024:
- Creative Arts Secondary School
- Rondo Complex: Capitol Hill and Benjamin E. Mays
Completed projects:
- Johnson Senior High School - completed September 2023
- Highland Park Middle School - completed October 2024
- Maxfield Elementary - completed January 2024
- Mississippi Creative Arts - completed October 2024
Project type: Kitchen upgrade
Phase: Planning
Project budget: $3,052,402; funded by American Rescue Plan, COVID-19 relief federal funding
Timeline: Completed August 2024
Sites: Education and Operations Services (August 2024)
Project type: Windows replacement
Phase: Closeout/complete
Project budget: $1,567,500
Timeline: 2021-2022 (completed)
Sites: Riverview; see monthly progress report: December 2022
Project type: Roof replacement
Phase: Closeout/complete
Project budget: $5,000,000
Timeline: Closeout fall 2022 (complete)
Sites: Bridge View; see monthly progress report: December 2022
Project type: Fire alarm/fire safety replacement
Phase: Planning and design ongoing
Project budget: TBD
Timeline: Ongoing
Sites: Various (no progress report)
Project type: Instructional audio visual installation
Phase: Planning and design ongoing
Project budget: TBD
Timeline: Ongoing
Sites: Various (no progress report)